This WBS was created on 05/29/1999.
This project is transitioning from the development to the support and maintenance phase. This will thus be the last WBS posted. Additional tasks will be handled through the monthly project meetings and presentations to the Run II Computing meetings. The packaging of products into KITS is a maintenance task. Work may occur for case tools - but only if the priority requests occur.
Project Start Date: Jan 1 '98
Project Finish Date: Dec 1
'99
|
|
|||||
| 1 | Configuration Management |
|
|
55%
|
|
| 1.1 | Meetings and Coordination |
|
|
50%
|
|
| 1.2 | C++ Deployment and Support - Unix/linux only |
|
|
48%
|
|
| 1.2.1 | KAI Compiler and Debugger |
|
JPP[0.5] |
48%
|
|
| 1.2.1.1 | Kai packaging, fixing and added value |
|
|
100%
|
|
| 1.2.1.2 | Kai vendor liaison |
|
|
50%
|
|
| 1.2.1.3 | Kai Debugger Support |
|
|
40%
|
|
| 1.2.2 | SGI Compilers |
|
JPP[0.2] |
0%
|
|
| 1.2.2.1 | IRIX C++ V7.2.1 testing and certification |
|
|
0%
|
|
| 1.2.3 | EGCS ? |
|
JPP[0.3] |
0%
|
|
| 1.2.3.1 | EGCS vendor liaison |
|
|
0%
|
|
| 1.2.3.2 | EGCS testing and certification |
|
|
0%
|
|
| 1.2.3.3 | EGCS packaging and deployment |
|
|
0%
|
|
| 1.2.3.4 | Support and consulting |
|
|
0%
|
|
| 1.3 | NT C++ Compiler Support |
|
JPP[0.2] |
0%
|
|
| 1.4 | SoftRelTools |
|
JPP |
95%
|
|
| 1.4.1 | SoftRelTools for KAI 3.3 |
|
|
100%
|
|
| 1.4.2 | SoftRelTools for EGCS |
|
|
100%
|
|
| 1.4.3 | SoftRelTools ToDo List |
|
|
94%
|
|
| 1.4.4 | Understand and document error logger |
|
|
100%
|
|
| 1.4.5 | Develop Dependency Tool |
|
|
100%
|
|
| 1.4.6 | Include and integrate package list |
|
|
100%
|
|
| 1.5 | ups/upd |
|
JPP[0.2] |
80%
|
|
| 1.5.1 | Finish upd regression tests |
|
|
50%
|
|
| 1.5.2 | Document upd and kits |
|
|
100%
|
|
| 1.5.3 | cdf and d0 distribution scripts |
|
|
80%
|
|
| 1.6 | Purify |
|
JPP[0.05] |
100%
|
|
| 1.6.1 | Package for KITS |
|
|
100%
|
|
| 1.7 | NOGO - Insure++ |
|
|
100%
|
|
| 1.7.1 | Get latest version and determine utility |
|
|
100%
|
|
| 1.8 | Graphical Designer |
|
JPP[0.3] |
10%
|
|
| 1.8.1 | GdPro V3.0 testing and deployment |
|
|
10%
|
|
| 1.8.2 | Add value for reporting |
|
|
0%
|
|
| 1.9 | Rational Rose - if requested |
|
|
0%
|
|
| 1.10 | Java Support - if requested |
|
|
80%
|
|
| 1.10.1 | Evaluate what versions and Java toolkits to support |
|
|
80%
|
|
| 1.10.2 | Package Java Development Kits and put in Kits |
|
|
80%
|
|
| 1.10.3 | Java debuggers - understand and support |
|
|
0%
|
|
| 1.11 | Corba Support - if requested |
|
|
30%
|
|
| 1.11.1 | Decide which versions of Corba to put in kits |
|
|
30%
|
|
| 1.11.2 | Put Corba in kits |
|
|
30%
|
|
|
||
| JPP |
2
|
2.3
|