Installation is going well. They indicate they are on schedule. The original estimate was for 26 WORK days to build the D0 system, 8 additional work days to do the CDF upgrade.

The four mammoth drives for Genser are supposed to be here this week. If they don't show up I'll ask the vendor for an update.