storage management


Project Start Date: Thu 07/29/99
Project Finish Date: Wed 12/15/99

Tasks

ID

Task Name

Duration

Start

Finish

Resource Names

% Complete

1

Interim System

88 days

Thu 07/29/99

Tue 11/30/99

 

92%

2

buy ram

1 day

Thu 07/29/99

Thu 07/29/99

DJHOLM

100%

3

produce partition plan

1 day

Thu 07/29/99

Thu 07/29/99

bakken

100%

4

load linux and configure system

4 days

Fri 07/30/99

Wed 08/04/99

Chinese visitor

100%

5

analyze tune xntp

0.5 days

Fri 08/06/99

Fri 08/06/99

 

0%

6

deal w/ loadable modules, vai lilo config, etc

3 days

Tue 08/10/99

Thu 08/19/99

DJHOLM

100%

7

install new kernal

3 days

Fri 08/20/99

Tue 08/24/99

WALDMAN

100%

8

install 256 -> 512

0 days

Thu 08/05/99

Thu 08/05/99

DJHOLM

100%

9

OS support agreement

1 day

Tue 08/17/99

Tue 08/17/99

PETRAVICK

0%

10

IAD-> dsp support agreement

1 day

Mon 08/16/99

Mon 08/16/99

PETRAVICK

0%

11

support the watchdog

1 day

Fri 08/06/99

Fri 08/06/99

DJHOLM

0%

12

OS READY

0 days

Tue 08/24/99

Tue 08/24/99

 

0%

13

Request Network connection to cisco switch

11 days

Tue 08/03/99

Tue 08/17/99

ALCORN

100%

14

Install net connections

2 days

Wed 08/04/99

Thu 08/05/99

DHG

100%

15

Setup apache

0.5 days

Tue 08/24/99

Tue 08/24/99

BERMAN

100%

16

setup patrol

3 days

Tue 08/24/99

Thu 08/26/99

JONES

100%

17

setup CGI

0.5 days

Tue 08/24/99

Tue 08/24/99

BERMAN

100%

18

install backup mammoth

1 day

Wed 08/18/99

Wed 08/18/99

SYU

100%

19

specify backup tapes

1 day

Fri 07/30/99

Fri 07/30/99

DJHOLM

100%

20

buy backup tapes CD49018

1 day

Mon 08/02/99

Mon 08/02/99

DJHOLM

100%

21

specify cleaning tapes

1 day

Mon 08/02/99

Mon 08/02/99

bakken

100%

22

buy cleaning tapes

1 day

Tue 08/03/99

Tue 08/03/99

DJHOLM

100%

23

Install Enstore + dependent products

1 day

Mon 08/09/99

Mon 08/09/99

bakken

100%

24

pnfs setup -- all db except samson

1 day

Tue 08/10/99

Tue 08/10/99

bakken

100%

25

fix mounts on all client machines

1 day

Wed 08/11/99

Wed 08/11/99

OSS

100%

26

move SCSI , HBA, cables drives to interim

1 day

Wed 08/11/99

Wed 08/11/99

DJHOLM

100%

27

test and minimal operation

3 days

Fri 08/13/99

Tue 08/17/99

MOIBENKO

100%

28

available for DAB > robot demonstration

0 days

Tue 08/17/99

Tue 08/17/99

 

0%

29

available for ODS test

0 days

Tue 08/17/99

Tue 08/17/99

 

0%

30

able to IMPORT Mcc2 data

0 days

Fri 10/01/99

Fri 10/01/99

 

0%

31

MCC phase 2 reco

0 days

Tue 11/30/99

Tue 11/30/99

 

0%

32

 

 

 

 

 

 

33

FY99 REQUISITION

13 days

Thu 07/15/99

Mon 08/02/99

 

100%

34

order pc's -- cd48983

1 day

Thu 07/15/99

Thu 07/15/99

DJHOLM

100%

35

REQUISITON DISK, pc -- CD48984

1 day

Mon 08/02/99

Mon 08/02/99

DJHOLM

100%

36

Requistion ethernet NIC cards

0 days

Thu 07/29/99

Thu 07/29/99

DJHOLM

100%

37

Requistion Cyclades pod

1 day

Thu 07/29/99

Thu 07/29/99

DJHOLM

100%

38

 

 

 

 

 

 

39

10-mammoth-1

63 days

Thu 07/15/99

Tue 10/12/99

 

15%

40

Requsition mamoths

1 day

Thu 07/29/99

Fri 07/30/99

DIESBURG

100%

41

mammoths arrive

0 days

Fri 09/10/99

Fri 09/10/99

 

0%

42

specify labeled tapes

1 day

Thu 07/29/99

Thu 07/29/99

DIESBURG

100%

43

Requisition tapes

1 day

Fri 07/30/99

Fri 07/30/99

THIES,DIESBURG

100%

44

Tapes arrive

0 days

Fri 09/10/99

Fri 09/10/99

 

0%

45

tapes into library

2 days

Mon 09/13/99

Tue 09/14/99

SYU

0%

46

specify and requistion SCSI cables

1 day

Thu 08/05/99

Thu 08/05/99

DJHOLM

0%

47

SCSI cables arrive

0 days

Thu 08/19/99

Thu 08/19/99

 

0%

48

requistion ADAPTEC cards

1 day

Wed 08/04/99

Wed 08/04/99

DJHOLM

100%

49

sign off on adaptec - CD49199

1 day

Thu 08/05/99

Thu 08/05/99

DIESBURG

100%

50

5 PC's arrive

0 days

Thu 07/15/99

Thu 07/15/99

 

100%

51

10 adaptec arrive

0 days

Thu 09/16/99

Thu 09/16/99

 

100%

52

5 ethernet NIC ards arrive

0 days

Thu 07/29/99

Thu 07/29/99

 

100%

53

install mammoth 1s in library

1 day

Tue 09/28/99

Tue 09/28/99

ADIC

0%

54

rack 5 movers into stealth rack steath rack, hook up peripherals

1 day

Fri 09/17/99

Fri 09/17/99

ALCORN

0%

55

install os on one mover

5 days

Mon 09/20/99

Fri 09/24/99

CSIEH

0%

56

install enstore on one mover

5 days

Mon 09/27/99

Fri 10/01/99

bakken

0%

57

install patrol on one mover

5 days

Wed 10/06/99

Tue 10/12/99

ALCORN

0%

58

test one mover

3 days

Mon 10/04/99

Wed 10/06/99

bakken

0%

59

Clone, tweak install on four movers

1 day

Mon 10/04/99

Mon 10/04/99

ALCORN

0%

60

Test and debug four movers

3 days

Thu 10/07/99

Mon 10/11/99

bakken

0%

61

analyze, tune xntp

1 day

Tue 10/05/99

Tue 10/05/99

CSEIH

0%

62

 

 

 

 

 

 

63

final-system

58 days

Thu 07/29/99

Mon 10/18/99

 

13%

64

Disks arrive

0 days

Thu 07/29/99

Thu 07/29/99

 

0%

65

pc's arrive

0 days

Thu 08/26/99

Thu 08/26/99

 

0%

66

cyclades arrives CD48985

0 days

Thu 07/29/99

Thu 07/29/99

 

0%

67

rack pc's

1 day

Fri 08/27/99

Fri 08/27/99

JONES

0%

68

install os

5 days

Tue 09/14/99

Mon 09/27/99

CSIEH

0%

69

analyze, tune xntp

1 day

Tue 09/28/99

Tue 09/28/99

CSEIH

0%

70

install web

1 day

Wed 09/29/99

Wed 09/29/99

BERMAN

0%

71

install enstore and pnfs

5 days

Tue 10/12/99

Mon 10/18/99

bakken

0%

72

install patrol

5 days

Tue 09/28/99

Tue 10/05/99

ALCORN

0%

73

install cgi

1 day

Tue 09/28/99

Tue 09/28/99

BERMAN

0%

74

setup console server pod

1 day

Thu 07/29/99

Thu 07/29/99

DHG

0%

75

setup console server software

2 days

Fri 07/30/99

Mon 08/02/99

SYU

0%

76

specify rack

1 day

Fri 07/30/99

Fri 07/30/99

DJHOLM

100%

77

Notice we have 1 rack

1 day

Thu 08/12/99

Thu 08/12/99

MACNERLAND

100%

78

Paint and Drill Rack

1 day

Fri 08/13/99

Fri 08/13/99

MACNERLAND

100%

79

setup rack

0 days

Mon 08/16/99

Mon 08/16/99

MACNERLAND

100%

80

order networking

1 day

Tue 08/17/99

Tue 08/17/99

ALCORN

100%

81

Install console cabling

1 day

Wed 08/18/99

Wed 08/18/99

DHG

0%

82

install networking

4 days

Wed 09/08/99

Mon 09/13/99

DHG

0%

83

 

 

 

 

 

 

84

SMWG Drives

47 days

Fri 09/17/99

Mon 11/22/99

 

0%

85

order scsi hba

1 day

Mon 10/04/99

Mon 10/04/99

DJHOLM

0%

86

signoff

1 day

Tue 10/05/99

Tue 10/05/99

DIESBURG

0%

87

hba arrives

0 days

Tue 11/16/99

Tue 11/16/99

 

0%

88

order SCSI cables

1 day

Tue 10/05/99

Tue 10/05/99

DJHOLM

0%

89

SCSI cables arrive

0 days

Tue 10/19/99

Tue 10/19/99

 

0%

90

SMWG decision

0 days

Fri 10/01/99

Fri 10/01/99

DIESBURG

0%

91

Requsition SMWG drives + installation

1 day

Mon 10/04/99

Mon 10/04/99

DIESBURG

0%

92

SMWG drives arrive

0 days

Mon 11/15/99

Mon 11/15/99

 

0%

93

install SMWG drives in library

4 days

Wed 11/17/99

Mon 11/22/99

ADIC

0%

94

burn-in testing

5 days

Fri 09/17/99

Thu 09/23/99

bakken

0%

95

 

 

 

 

 

 

96

STK eagle system

116 days

Wed 07/07/99

Wed 12/15/99

 

18%

97

begin to concentare on this

0 days

Wed 12/01/99

Wed 12/01/99

 

0%

98

Negotiate space and Power

1 day

Fri 07/30/99

Fri 07/30/99

ALCORN

100%

99

specify rack

1 day

Mon 08/02/99

Mon 08/02/99

DJHOLM

100%

100

order rack

1 day

Tue 08/03/99

Tue 08/03/99

MACNERLAND

100%

101

setup rack

0 days

Wed 12/01/99

Wed 12/01/99

DHG

100%

102

order networking

1 day

Thu 07/29/99

Thu 07/29/99

ALCORN

100%

103

install networking

4 days

Thu 12/02/99

Tue 12/07/99

DHG

0%

104

order scsi hba

1 day

Thu 12/02/99

Thu 12/02/99

DJHOLM

0%

105

hba arrives

0 days

Thu 07/29/99

Thu 07/29/99

 

0%

106

order cables

1 day

Wed 12/01/99

Wed 12/01/99

DJHOLM

0%

107

cables arrive

0 days

Wed 12/15/99

Wed 12/15/99

 

0%

108

reqisition drives and media

1 day

Wed 07/07/99

Wed 07/07/99

ALCORN

100%

109

install drives and media

1 day

Thu 09/09/99

Thu 09/09/99

STK

0%

110

order pc's

1 day

Fri 07/16/99

Fri 07/16/99

DJHOLM

100%

111

pc's arrive

0 days

Fri 08/27/99

Fri 08/27/99

 

100%

112

rack pc's

1 day

Wed 12/01/99

Wed 12/01/99

JONES

100%

113

install os

5 days

Thu 12/02/99

Wed 12/08/99

CSIEH

0%

114

analyze, tune xntp

1 day

Thu 12/09/99

Thu 12/09/99

CSEIH

0%

115

install web

1 day

Fri 12/10/99

Fri 12/10/99

BERMAN

0%

116

install enstore and pnfs

5 days

Thu 12/09/99

Wed 12/15/99

bakken

0%

117

install patrol

5 days

Thu 12/09/99

Wed 12/15/99

ALCORN

0%

118

install cgi

1 day

Thu 12/09/99

Thu 12/09/99

BERMAN

0%

119

setup console server pod

1 day

Wed 12/01/99

Wed 12/01/99

DHG

0%

120

setup console server software

2 days

Thu 12/02/99

Fri 12/03/99

SYU

0%

121

burn-in testing

5 days

Thu 12/02/99

Wed 12/08/99

bakken

0%