D0_RunII_project


Project Start Date: Tue 7/6/99
Project Finish Date: Wed 12/1/99

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
D02KA
88 daysTue 7/6/99Thu 11/4/99 93%
2
Wait for equipment
5 daysTue 7/6/99Mon 7/12/99 100%
3
Installations
3 daysThu 7/15/99Mon 7/19/99 100%
4
Fibre-Channel Cards
1 dayThu 7/15/99Thu 7/15/99CDSR2[25%]100%
5
Gigabit Ethernet
1 dayThu 7/15/99Thu 7/15/99CDSR2[25%]100%
6
Downtime problems - Disk failures/Chassis
1 dayFri 7/16/99Fri 7/16/99CDSR2100%
7
Raid disks
1 dayMon 7/19/99Mon 7/19/99CDSR2[25%]100%
8
Fibre Disk Rack
1 dayMon 7/19/99Mon 7/19/99CDSR2[25%]100%
9
Understanding Fibre-Channel Disk Technology
3 daysWed 7/28/99Tue 9/28/99CDSR2[50%]100%
10
Raid configuration/partitioning
2 daysWed 8/25/99Thu 8/26/99CDSR2[50%]100%
11
Kernal Modes for XLV wait for reboot
6 daysThu 7/22/99Thu 7/29/99 100%
12
Fibre Channel Disk problems (SGI 2 BUGS)/Patch
6 daysFri 7/30/99Fri 8/6/99 100%
13
Wait for reboot
1 dayMon 8/9/99Mon 8/9/99 100%
14
Export current homes
1 dayTue 7/20/99Tue 7/20/99CDSR2[10%]100%
15
Identify RunII areas to export
4 daysMon 7/26/99Thu 7/29/99D0100%
16
Export Current projects/tmps (RunII)
1 dayFri 7/30/99Fri 7/30/99CDSR2[10%]100%
17
User Notification
3 daysWed 8/25/99Fri 8/27/99 100%
18
Move Homes Expansion consistent with backup
10 daysMon 8/30/99Fri 9/10/99CDSR2100%
19
Move D02ka to Gigabit Ethernet
1 dayMon 10/11/99Tue 10/12/99 0%
20
Balance of home made available
1 dayThu 11/4/99Thu 11/4/99CDSR20%
21
Add link to local
1 dayTue 9/14/99Tue 9/14/99CDSR20%
22
Data Disks (prj/tmp) Migration
54.3 daysThu 7/29/99Thu 10/14/99 92%
23
Allocate Hardware
1 dayThu 7/29/99Fri 7/30/99D0100%
24
Install
29.5 daysWed 8/4/99Tue 9/14/99 100%
25
File System Plan/Identify RunII Data
1 dayWed 8/4/99Wed 8/4/99D0100%
26
Implement Plan
1 dayThu 8/19/99Thu 8/19/99CDSR2100%
27
User Notification
5 daysFri 8/20/99Thu 8/26/99 100%
28
Copy to new disks
15 daysMon 8/23/99Tue 9/14/99CDSR2-2100%
29
Old Disk unavaialble
0 daysTue 9/14/99Tue 9/14/99CDSR2100%
30
Move disks(cable) D0MINO
2 daysTue 10/12/99Thu 10/14/99CDSR20%
31      
32
D0MINO
74.3 daysTue 7/6/99Mon 10/18/99 63%
33
D0MINO Burnin
10 daysTue 7/6/99Mon 7/19/99 100%
34
SGI Hardware Tests
3 daysTue 7/6/99Thu 7/8/99SGI100%
35
Hardware Configuration Plan
1 dayFri 7/9/99Fri 7/9/99CDS-D0100%
36
Optional Hardware Configuration
1 dayMon 7/12/99Mon 7/12/99CDS-D0100%
37
Disk Installation/Testing
2 daysTue 7/13/99Wed 7/14/99CDSR2100%
38
Network Installation
3 daysThu 7/15/99Mon 7/19/99NET100%
39
System disk set (Plexing)
2 daysMon 7/26/99Tue 7/27/99CDSR2[50%]100%
40
Install ssh/tcpwrappers
1 dayWed 7/28/99Wed 7/28/99CDSR2[10%]100%
41
System Unavailable (FCC Air Conditioning)
2 daysThu 7/29/99Fri 7/30/99 100%
42
Mount User homes
1 dayMon 8/2/99Mon 8/2/99CDSR2[10%]100%
43
Mount RunII Areas
1 dayTue 8/3/99Tue 8/3/99CDSR2[10%]100%
44
D0MINO Software
67.3 daysThu 7/15/99Mon 10/18/99 56%
45
SHARE
30 daysTue 8/17/99Mon 9/27/99CDSR20%
46
Wait for software
30 daysTue 8/17/99Mon 9/27/99 0%
47
Patrol
3 daysWed 8/25/99Fri 8/27/99CDSR2-20%
48
NLBS (Interactive Network)
7 daysThu 7/15/99Fri 7/23/99 100%
49
Configuration Plan
1 dayThu 7/15/99Thu 7/15/99CDS-D0100%
50
Installation
1 dayMon 7/19/99Mon 7/19/99CDSR2[10%]100%
51
Investigation/Implementation
3 daysTue 7/20/99Thu 7/22/99CDSR2[50%]100%
52
Testing
1 dayFri 7/23/99Fri 7/23/99CDSR2100%
53
Co-Pilot
37 daysMon 7/26/99Tue 9/14/99CDSR295%
54
Wait for software
35 daysMon 7/26/99Fri 9/10/99 100%
55
Install
1 dayMon 9/13/99Mon 9/13/99 0%
56
configure?
1 dayTue 9/14/99Tue 9/14/99 0%
57
LSF
49.3 daysWed 8/4/99Tue 10/12/99 57%
58
License
3 daysWed 8/4/99Fri 8/6/99ISD100%
59
LSF General Configuration Specs
1 dayMon 8/23/99Mon 8/23/99CDS-D0100%
60
LSF Configuration
1 dayMon 8/30/99Mon 8/30/99CDSR2-20%
61
LSF SAM/ENSTORE Configuration
1 dayFri 8/13/99Fri 8/13/99CDS-D00%
62
LSF Configuration
1 dayMon 10/11/99Tue 10/12/99CDSR20%
63
Compilers
1 dayThu 7/22/99Thu 7/22/99 100%
64
Licenses
1 dayThu 7/22/99Thu 7/22/99SGI100%
65
UPS Products (NFS TEMP)
59.3 daysTue 7/27/99Mon 10/18/99 67%
66
Initial mount from d02ka
1 dayTue 7/27/99Tue 7/27/99CDSR2[10%]100%
67
UPS configuration on D0mino
30.3 daysMon 9/6/99Mon 10/18/99 60%
68
FMB
1 dayThu 10/14/99Fri 10/15/99 0%
69
Installation
1 dayThu 10/14/99Fri 10/15/99CDSR2[50%]0%
70
Configure System Backup
1 dayThu 10/14/99Fri 10/15/99CDSR2[50%]0%
71
KAI
5 daysMon 9/6/99Fri 9/10/99 100%
72
Installation
1 dayMon 9/6/99Mon 9/6/99CDSR2[50%]100%
73
Lincense
1 dayFri 9/10/99Fri 9/10/99?100%
74
D0UPS
1 dayFri 10/15/99Mon 10/18/99 100%
75
Initial mount from d02ka
1 dayFri 10/15/99Mon 10/18/99CDSR2[50%]100%
76      
77      
78
D0MINO Prod Anal Disk
80 daysTue 8/3/99Mon 11/22/99 67%
79
Allocate Hardware
1 dayTue 8/3/99Tue 8/3/99D0100%
80
Enstore Disk ( 2.75 TB - SLOP )
40.3 daysFri 8/6/99Fri 10/1/99 0%
81
File System Plan
1 dayFri 8/6/99Fri 8/6/99CDS-D00%
82
Implement Plan
3 daysTue 9/28/99Fri 10/1/99CDSR20%
83
Scratch Disk ( 0.25 TB )
51 daysMon 9/13/99Mon 11/22/99 0%
84
File System Plan
1 dayMon 9/13/99Mon 9/13/99CDS-D00%
85
Implement Plan
1 dayMon 11/22/99Mon 11/22/99CDSR20%
86
TMP Disk ( 1.0 TB )
11 daysMon 8/30/99Mon 9/13/99 100%
87
File System Plan
1 dayMon 8/30/99Mon 8/30/99CDS-D0100%
88
Implement Plan
3 daysThu 9/9/99Mon 9/13/99CDSR2100%
89
Project (legacy) Disk ( 1.0 TB )
36.5 daysMon 8/9/99Tue 9/28/99 100%
90
File System Plan
1 dayMon 8/9/99Mon 8/9/99CDS-D0100%
91
Implement Plan
10 daysTue 9/14/99Tue 9/28/99CDSR2100%
92
D0Dist ( 108 GB )
17 daysFri 9/10/99Mon 10/4/99 67%
93
File System Plan
1 dayFri 9/10/99Fri 9/10/99CDS-D0100%
94
Implement Plan
1 dayMon 9/13/99Mon 9/13/99CDSR2100%
95
Copy D0DIST from D02KA
1 dayMon 10/4/99Mon 10/4/99D00%
96      
97
Final UPS Products ( 36 GB )
2 daysWed 10/13/99Fri 10/15/99 0%
98
UPS Products
1 dayWed 10/13/99Thu 10/14/99CDSR20%
99
D0 UPS Products
1 dayThu 10/14/99Fri 10/15/99CDSR20%
100      
101
D0TEST
37.3 daysFri 8/20/99Tue 10/12/99 10%
102
Split Rack From Domino
1 dayFri 8/20/99Fri 8/20/99CDSR2100%
103
Understanding Multi interface problem
1 dayMon 8/23/99Mon 8/23/99CDSR20%
104
Gigabit Ethernet
1 dayTue 8/24/99Tue 8/24/99 0%
105
Request installation
1 dayTue 8/24/99Tue 8/24/99CDSR20%
106
Install addition Gigabit Ethernets (cabling from d0mino)
1 dayTue 8/24/99Tue 8/24/99SGI0%
107
Test filesystems
1 dayWed 8/25/99Wed 8/25/99 0%
108
On D02ka
1 dayWed 8/25/99Wed 8/25/99CDSR20%
109
On D0test
1 dayWed 8/25/99Wed 8/25/99CDSR20%
110
Test Gigabit Ethernet
1 dayFri 10/8/99Mon 10/11/99CDSR20%
111
Fast Ethernet
1 dayMon 10/11/99Tue 10/12/99 0%
112
Install Quad Ethernet board
1 dayMon 10/11/99Tue 10/12/99CDSR20%
113
Request/Move connections
1 dayMon 10/11/99Tue 10/12/99CDSR20%
114
NLBS testing
1 dayMon 10/11/99Tue 10/12/99CDSR20%
115      
116
Backups
68 daysMon 8/2/99Wed 11/3/99 6%
117
Backup plan
3 daysMon 8/2/99Wed 8/4/99CDS-D0100%
118
Purchase Hardware/Media
1 dayThu 8/5/99Thu 8/5/99CDS-D0100%
119
Wait for equipment
60 daysFri 8/6/99Thu 10/28/99 0%
120
Install/test/Configure FMB/Juke
3 daysFri 10/29/99Tue 11/2/99CDSR20%
121
Configure for backup
1 dayWed 11/3/99Wed 11/3/99CDSR20%
122      
123
NIS
72 daysThu 7/29/99Fri 11/5/99 7%
124
Configuration problems (NLBS)
12 daysThu 7/29/99Fri 8/13/99 0%
125
D0mino NIS Slave (?) / Configure NIS
1 dayMon 8/16/99Mon 8/16/99CDSR2[20%]100%
126
D0mino Master
1 dayFri 11/5/99Fri 11/5/99CDSR20%
127      
128
SAM
43.7 daysFri 10/1/99Wed 12/1/99 0%
129
Initial Testing
1 dayFri 10/1/99Mon 10/4/99 0%
130
Testing w/ LSF
1 dayTue 10/12/99Wed 10/13/99 0%
131
Testing w/Enstore
1 dayWed 12/1/99Wed 12/1/99 0%
132      
133
ENSTORE
57 daysMon 9/13/99Tue 11/30/99 0%
134
Network (Gigabit Ethernet) Installation
1 dayMon 9/13/99Mon 9/13/99NET0%
135
Network Configuration
1 dayTue 10/5/99Wed 10/6/99CDSR20%
136
Testing
1 dayTue 11/23/99Tue 11/23/99ISD0%
137
MPADMIN/SYSMP
5 daysWed 11/24/99Tue 11/30/99ISD0%
138      
139
D0MINO Early Bird
5 daysMon 9/13/99Fri 9/17/99 0%
140
D0MINO General Availability
1 dayThu 11/4/99Thu 11/4/99 0%
141
D0MINO Fully Functionable
1 dayWed 12/1/99Wed 12/1/99 0%

Resources

IDNameGroupMax UnitsPeak Units
1CDSR2 100%450%
2CDSR2-2 100%200%
3ISD 100%100%
4D0 100%100%
5? 100%100%
6NET 100%100%
7CDS-D0 100%100%
8SGI 1,000%100%

Assignments

Task IDTask NameResource NameWorkStartFinish% Work Complete
4Fibre-Channel CardsCDSR22 hrsThu 7/15/99Thu 7/15/99100%
5Gigabit Ethernet CDSR22 hrsThu 7/15/99Thu 7/15/99100%
6Downtime problems - Disk failures/ChassisCDSR24 hrsFri 7/16/99Fri 7/16/99100%
7Raid disksCDSR22 hrsMon 7/19/99Mon 7/19/99100%
8Fibre Disk RackCDSR22 hrsMon 7/19/99Mon 7/19/99100%
9Understanding Fibre-Channel Disk TechnologyCDSR212 hrsWed 7/28/99Tue 9/28/99100%
10Raid configuration/partitioning CDSR28 hrsWed 8/25/99Thu 8/26/99100%
14Export current homes CDSR20.8 hrsTue 7/20/99Tue 7/20/99100%
15Identify RunII areas to export D032 hrsMon 7/26/99Thu 7/29/99100%
16Export Current projects/tmps (RunII)CDSR20.8 hrsFri 7/30/99Fri 7/30/99100%
18Move Homes Expansion consistent with backupCDSR280 hrsMon 8/30/99Fri 9/10/99100%
20Balance of home made available CDSR28 hrsThu 11/4/99Thu 11/4/990%
21Add link to localCDSR28 hrsTue 9/14/99Tue 9/14/990%
23Allocate HardwareD00 hrsThu 7/29/99Thu 7/29/99100%
25File System Plan/Identify RunII DataD08 hrsWed 8/4/99Wed 8/4/99100%
26Implement PlanCDSR28 hrsThu 8/19/99Thu 8/19/99100%
28Copy to new disksCDSR2-2120 hrsTue 8/24/99Tue 9/14/99100%
29Old Disk unavaialbleCDSR20 hrsTue 9/14/99Tue 9/14/99100%
30Move disks(cable) D0MINOCDSR216 hrsTue 10/12/99Thu 10/14/990%
34SGI Hardware TestsSGI24 hrsTue 7/6/99Thu 7/8/99100%
35Hardware Configuration PlanCDS-D08 hrsFri 7/9/99Fri 7/9/99100%
36Optional Hardware ConfigurationCDS-D08 hrsMon 7/12/99Mon 7/12/99100%
37Disk Installation/TestingCDSR216 hrsTue 7/13/99Wed 7/14/99100%
38Network InstallationNET24 hrsThu 7/15/99Mon 7/19/99100%
39System disk set (Plexing)CDSR28 hrsMon 7/26/99Tue 7/27/99100%
40Install ssh/tcpwrappersCDSR20.8 hrsWed 7/28/99Wed 7/28/99100%
42Mount User homes CDSR20.8 hrsMon 8/2/99Mon 8/2/99100%
43Mount RunII AreasCDSR20.8 hrsTue 8/3/99Tue 8/3/99100%
45SHARE CDSR2240 hrsTue 8/17/99Mon 9/27/990%
47PatrolCDSR2-224 hrsWed 8/25/99Fri 8/27/990%
49Configuration PlanCDS-D08 hrsThu 7/15/99Thu 7/15/99100%
50InstallationCDSR24 hrsMon 7/19/99Mon 7/19/99100%
51Investigation/Implementation CDSR212 hrsTue 7/20/99Thu 7/22/99100%
52TestingCDSR28 hrsFri 7/23/99Fri 7/23/99100%
53Co-PilotCDSR2296 hrsMon 7/26/99Tue 9/14/9995%
58LicenseISD24 hrsWed 8/4/99Fri 8/6/99100%
59LSF General Configuration SpecsCDS-D08 hrsMon 8/23/99Mon 8/23/99100%
60LSF ConfigurationCDSR2-28 hrsMon 8/30/99Mon 8/30/990%
61LSF SAM/ENSTORE ConfigurationCDS-D08 hrsFri 8/13/99Fri 8/13/990%
62LSF ConfigurationCDSR28 hrsMon 10/11/99Tue 10/12/990%
64LicensesSGI8 hrsThu 7/22/99Thu 7/22/99100%
66Initial mount from d02kaCDSR20.8 hrsTue 7/27/99Tue 7/27/99100%
69InstallationCDSR24 hrsThu 10/14/99Fri 10/15/990%
70Configure System BackupCDSR24 hrsThu 10/14/99Fri 10/15/990%
72InstallationCDSR24 hrsMon 9/6/99Mon 9/6/99100%
73Lincense?8 hrsFri 9/10/99Fri 9/10/99100%
75Initial mount from d02kaCDSR24 hrsFri 10/15/99Mon 10/18/99100%
79Allocate HardwareD08 hrsTue 8/3/99Tue 8/3/99100%
81File System PlanCDS-D08 hrsFri 8/6/99Fri 8/6/990%
82Implement PlanCDSR224 hrsTue 9/28/99Fri 10/1/990%
84File System PlanCDS-D08 hrsMon 9/13/99Mon 9/13/990%
85Implement PlanCDSR28 hrsMon 11/22/99Mon 11/22/990%
87File System PlanCDS-D08 hrsMon 8/30/99Mon 8/30/99100%
88Implement PlanCDSR224 hrsThu 9/9/99Mon 9/13/99100%
90File System PlanCDS-D08 hrsMon 8/9/99Mon 8/9/99100%
91Implement PlanCDSR280 hrsTue 9/14/99Tue 9/28/99100%
93File System PlanCDS-D08 hrsFri 9/10/99Fri 9/10/99100%
94Implement PlanCDSR28 hrsMon 9/13/99Mon 9/13/99100%
95Copy D0DIST from D02KAD08 hrsMon 10/4/99Mon 10/4/990%
98UPS ProductsCDSR28 hrsWed 10/13/99Thu 10/14/990%
99D0 UPS ProductsCDSR28 hrsThu 10/14/99Fri 10/15/990%
102Split Rack From DominoCDSR28 hrsFri 8/20/99Fri 8/20/99100%
103Understanding Multi interface problemCDSR28 hrsMon 8/23/99Mon 8/23/990%
105Request installationCDSR28 hrsTue 8/24/99Tue 8/24/990%
106Install addition Gigabit Ethernets (cabling from d0mino)SGI8 hrsTue 8/24/99Tue 8/24/990%
108On D02kaCDSR28 hrsWed 8/25/99Wed 8/25/990%
109On D0testCDSR28 hrsWed 8/25/99Wed 8/25/990%
110Test Gigabit Ethernet CDSR28 hrsFri 10/8/99Mon 10/11/990%
112Install Quad Ethernet boardCDSR28 hrsMon 10/11/99Tue 10/12/990%
113Request/Move connectionsCDSR28 hrsMon 10/11/99Tue 10/12/990%
114NLBS testing CDSR28 hrsMon 10/11/99Tue 10/12/990%
117Backup planCDS-D024 hrsMon 8/2/99Wed 8/4/99100%
118Purchase Hardware/MediaCDS-D08 hrsThu 8/5/99Thu 8/5/99100%
120Install/test/Configure FMB/JukeCDSR224 hrsFri 10/29/99Tue 11/2/990%
121Configure for backupCDSR28 hrsWed 11/3/99Wed 11/3/990%
125D0mino NIS Slave (?) / Configure NISCDSR21.6 hrsMon 8/16/99Mon 8/16/99100%
126D0mino MasterCDSR28 hrsFri 11/5/99Fri 11/5/990%
134Network (Gigabit Ethernet) InstallationNET8 hrsMon 9/13/99Mon 9/13/990%
135Network ConfigurationCDSR28 hrsTue 10/5/99Wed 10/6/990%
136TestingISD8 hrsTue 11/23/99Tue 11/23/990%
137MPADMIN/SYSMPISD40 hrsWed 11/24/99Tue 11/30/990%