Project Start Date: Tue 7/6/99
Project Finish Date: Wed 12/1/99
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | D02KA | 88 days | Tue 7/6/99 | Thu 11/4/99 | 93% | |
| 2 | Wait for equipment | 5 days | Tue 7/6/99 | Mon 7/12/99 | 100% | |
| 3 | Installations | 3 days | Thu 7/15/99 | Mon 7/19/99 | 100% | |
| 4 | Fibre-Channel Cards | 1 day | Thu 7/15/99 | Thu 7/15/99 | CDSR2[25%] | 100% |
| 5 | Gigabit Ethernet | 1 day | Thu 7/15/99 | Thu 7/15/99 | CDSR2[25%] | 100% |
| 6 | Downtime problems - Disk failures/Chassis | 1 day | Fri 7/16/99 | Fri 7/16/99 | CDSR2 | 100% |
| 7 | Raid disks | 1 day | Mon 7/19/99 | Mon 7/19/99 | CDSR2[25%] | 100% |
| 8 | Fibre Disk Rack | 1 day | Mon 7/19/99 | Mon 7/19/99 | CDSR2[25%] | 100% |
| 9 | Understanding Fibre-Channel Disk Technology | 3 days | Wed 7/28/99 | Tue 9/28/99 | CDSR2[50%] | 100% |
| 10 | Raid configuration/partitioning | 2 days | Wed 8/25/99 | Thu 8/26/99 | CDSR2[50%] | 100% |
| 11 | Kernal Modes for XLV wait for reboot | 6 days | Thu 7/22/99 | Thu 7/29/99 | 100% | |
| 12 | Fibre Channel Disk problems (SGI 2 BUGS)/Patch | 6 days | Fri 7/30/99 | Fri 8/6/99 | 100% | |
| 13 | Wait for reboot | 1 day | Mon 8/9/99 | Mon 8/9/99 | 100% | |
| 14 | Export current homes | 1 day | Tue 7/20/99 | Tue 7/20/99 | CDSR2[10%] | 100% |
| 15 | Identify RunII areas to export | 4 days | Mon 7/26/99 | Thu 7/29/99 | D0 | 100% |
| 16 | Export Current projects/tmps (RunII) | 1 day | Fri 7/30/99 | Fri 7/30/99 | CDSR2[10%] | 100% |
| 17 | User Notification | 3 days | Wed 8/25/99 | Fri 8/27/99 | 100% | |
| 18 | Move Homes Expansion consistent with backup | 10 days | Mon 8/30/99 | Fri 9/10/99 | CDSR2 | 100% |
| 19 | Move D02ka to Gigabit Ethernet | 1 day | Mon 10/11/99 | Tue 10/12/99 | 0% | |
| 20 | Balance of home made available | 1 day | Thu 11/4/99 | Thu 11/4/99 | CDSR2 | 0% |
| 21 | Add link to local | 1 day | Tue 9/14/99 | Tue 9/14/99 | CDSR2 | 0% |
| 22 | Data Disks (prj/tmp) Migration | 54.3 days | Thu 7/29/99 | Thu 10/14/99 | 92% | |
| 23 | Allocate Hardware | 1 day | Thu 7/29/99 | Fri 7/30/99 | D0 | 100% |
| 24 | Install | 29.5 days | Wed 8/4/99 | Tue 9/14/99 | 100% | |
| 25 | File System Plan/Identify RunII Data | 1 day | Wed 8/4/99 | Wed 8/4/99 | D0 | 100% |
| 26 | Implement Plan | 1 day | Thu 8/19/99 | Thu 8/19/99 | CDSR2 | 100% |
| 27 | User Notification | 5 days | Fri 8/20/99 | Thu 8/26/99 | 100% | |
| 28 | Copy to new disks | 15 days | Mon 8/23/99 | Tue 9/14/99 | CDSR2-2 | 100% |
| 29 | Old Disk unavaialble | 0 days | Tue 9/14/99 | Tue 9/14/99 | CDSR2 | 100% |
| 30 | Move disks(cable) D0MINO | 2 days | Tue 10/12/99 | Thu 10/14/99 | CDSR2 | 0% |
| 31 | ||||||
| 32 | D0MINO | 74.3 days | Tue 7/6/99 | Mon 10/18/99 | 63% | |
| 33 | D0MINO Burnin | 10 days | Tue 7/6/99 | Mon 7/19/99 | 100% | |
| 34 | SGI Hardware Tests | 3 days | Tue 7/6/99 | Thu 7/8/99 | SGI | 100% |
| 35 | Hardware Configuration Plan | 1 day | Fri 7/9/99 | Fri 7/9/99 | CDS-D0 | 100% |
| 36 | Optional Hardware Configuration | 1 day | Mon 7/12/99 | Mon 7/12/99 | CDS-D0 | 100% |
| 37 | Disk Installation/Testing | 2 days | Tue 7/13/99 | Wed 7/14/99 | CDSR2 | 100% |
| 38 | Network Installation | 3 days | Thu 7/15/99 | Mon 7/19/99 | NET | 100% |
| 39 | System disk set (Plexing) | 2 days | Mon 7/26/99 | Tue 7/27/99 | CDSR2[50%] | 100% |
| 40 | Install ssh/tcpwrappers | 1 day | Wed 7/28/99 | Wed 7/28/99 | CDSR2[10%] | 100% |
| 41 | System Unavailable (FCC Air Conditioning) | 2 days | Thu 7/29/99 | Fri 7/30/99 | 100% | |
| 42 | Mount User homes | 1 day | Mon 8/2/99 | Mon 8/2/99 | CDSR2[10%] | 100% |
| 43 | Mount RunII Areas | 1 day | Tue 8/3/99 | Tue 8/3/99 | CDSR2[10%] | 100% |
| 44 | D0MINO Software | 67.3 days | Thu 7/15/99 | Mon 10/18/99 | 56% | |
| 45 | SHARE | 30 days | Tue 8/17/99 | Mon 9/27/99 | CDSR2 | 0% |
| 46 | Wait for software | 30 days | Tue 8/17/99 | Mon 9/27/99 | 0% | |
| 47 | Patrol | 3 days | Wed 8/25/99 | Fri 8/27/99 | CDSR2-2 | 0% |
| 48 | NLBS (Interactive Network) | 7 days | Thu 7/15/99 | Fri 7/23/99 | 100% | |
| 49 | Configuration Plan | 1 day | Thu 7/15/99 | Thu 7/15/99 | CDS-D0 | 100% |
| 50 | Installation | 1 day | Mon 7/19/99 | Mon 7/19/99 | CDSR2[10%] | 100% |
| 51 | Investigation/Implementation | 3 days | Tue 7/20/99 | Thu 7/22/99 | CDSR2[50%] | 100% |
| 52 | Testing | 1 day | Fri 7/23/99 | Fri 7/23/99 | CDSR2 | 100% |
| 53 | Co-Pilot | 37 days | Mon 7/26/99 | Tue 9/14/99 | CDSR2 | 95% |
| 54 | Wait for software | 35 days | Mon 7/26/99 | Fri 9/10/99 | 100% | |
| 55 | Install | 1 day | Mon 9/13/99 | Mon 9/13/99 | 0% | |
| 56 | configure? | 1 day | Tue 9/14/99 | Tue 9/14/99 | 0% | |
| 57 | LSF | 49.3 days | Wed 8/4/99 | Tue 10/12/99 | 57% | |
| 58 | License | 3 days | Wed 8/4/99 | Fri 8/6/99 | ISD | 100% |
| 59 | LSF General Configuration Specs | 1 day | Mon 8/23/99 | Mon 8/23/99 | CDS-D0 | 100% |
| 60 | LSF Configuration | 1 day | Mon 8/30/99 | Mon 8/30/99 | CDSR2-2 | 0% |
| 61 | LSF SAM/ENSTORE Configuration | 1 day | Fri 8/13/99 | Fri 8/13/99 | CDS-D0 | 0% |
| 62 | LSF Configuration | 1 day | Mon 10/11/99 | Tue 10/12/99 | CDSR2 | 0% |
| 63 | Compilers | 1 day | Thu 7/22/99 | Thu 7/22/99 | 100% | |
| 64 | Licenses | 1 day | Thu 7/22/99 | Thu 7/22/99 | SGI | 100% |
| 65 | UPS Products (NFS TEMP) | 59.3 days | Tue 7/27/99 | Mon 10/18/99 | 67% | |
| 66 | Initial mount from d02ka | 1 day | Tue 7/27/99 | Tue 7/27/99 | CDSR2[10%] | 100% |
| 67 | UPS configuration on D0mino | 30.3 days | Mon 9/6/99 | Mon 10/18/99 | 60% | |
| 68 | FMB | 1 day | Thu 10/14/99 | Fri 10/15/99 | 0% | |
| 69 | Installation | 1 day | Thu 10/14/99 | Fri 10/15/99 | CDSR2[50%] | 0% |
| 70 | Configure System Backup | 1 day | Thu 10/14/99 | Fri 10/15/99 | CDSR2[50%] | 0% |
| 71 | KAI | 5 days | Mon 9/6/99 | Fri 9/10/99 | 100% | |
| 72 | Installation | 1 day | Mon 9/6/99 | Mon 9/6/99 | CDSR2[50%] | 100% |
| 73 | Lincense | 1 day | Fri 9/10/99 | Fri 9/10/99 | ? | 100% |
| 74 | D0UPS | 1 day | Fri 10/15/99 | Mon 10/18/99 | 100% | |
| 75 | Initial mount from d02ka | 1 day | Fri 10/15/99 | Mon 10/18/99 | CDSR2[50%] | 100% |
| 76 | ||||||
| 77 | ||||||
| 78 | D0MINO Prod Anal Disk | 80 days | Tue 8/3/99 | Mon 11/22/99 | 67% | |
| 79 | Allocate Hardware | 1 day | Tue 8/3/99 | Tue 8/3/99 | D0 | 100% |
| 80 | Enstore Disk ( 2.75 TB - SLOP ) | 40.3 days | Fri 8/6/99 | Fri 10/1/99 | 0% | |
| 81 | File System Plan | 1 day | Fri 8/6/99 | Fri 8/6/99 | CDS-D0 | 0% |
| 82 | Implement Plan | 3 days | Tue 9/28/99 | Fri 10/1/99 | CDSR2 | 0% |
| 83 | Scratch Disk ( 0.25 TB ) | 51 days | Mon 9/13/99 | Mon 11/22/99 | 0% | |
| 84 | File System Plan | 1 day | Mon 9/13/99 | Mon 9/13/99 | CDS-D0 | 0% |
| 85 | Implement Plan | 1 day | Mon 11/22/99 | Mon 11/22/99 | CDSR2 | 0% |
| 86 | TMP Disk ( 1.0 TB ) | 11 days | Mon 8/30/99 | Mon 9/13/99 | 100% | |
| 87 | File System Plan | 1 day | Mon 8/30/99 | Mon 8/30/99 | CDS-D0 | 100% |
| 88 | Implement Plan | 3 days | Thu 9/9/99 | Mon 9/13/99 | CDSR2 | 100% |
| 89 | Project (legacy) Disk ( 1.0 TB ) | 36.5 days | Mon 8/9/99 | Tue 9/28/99 | 100% | |
| 90 | File System Plan | 1 day | Mon 8/9/99 | Mon 8/9/99 | CDS-D0 | 100% |
| 91 | Implement Plan | 10 days | Tue 9/14/99 | Tue 9/28/99 | CDSR2 | 100% |
| 92 | D0Dist ( 108 GB ) | 17 days | Fri 9/10/99 | Mon 10/4/99 | 67% | |
| 93 | File System Plan | 1 day | Fri 9/10/99 | Fri 9/10/99 | CDS-D0 | 100% |
| 94 | Implement Plan | 1 day | Mon 9/13/99 | Mon 9/13/99 | CDSR2 | 100% |
| 95 | Copy D0DIST from D02KA | 1 day | Mon 10/4/99 | Mon 10/4/99 | D0 | 0% |
| 96 | ||||||
| 97 | Final UPS Products ( 36 GB ) | 2 days | Wed 10/13/99 | Fri 10/15/99 | 0% | |
| 98 | UPS Products | 1 day | Wed 10/13/99 | Thu 10/14/99 | CDSR2 | 0% |
| 99 | D0 UPS Products | 1 day | Thu 10/14/99 | Fri 10/15/99 | CDSR2 | 0% |
| 100 | ||||||
| 101 | D0TEST | 37.3 days | Fri 8/20/99 | Tue 10/12/99 | 10% | |
| 102 | Split Rack From Domino | 1 day | Fri 8/20/99 | Fri 8/20/99 | CDSR2 | 100% |
| 103 | Understanding Multi interface problem | 1 day | Mon 8/23/99 | Mon 8/23/99 | CDSR2 | 0% |
| 104 | Gigabit Ethernet | 1 day | Tue 8/24/99 | Tue 8/24/99 | 0% | |
| 105 | Request installation | 1 day | Tue 8/24/99 | Tue 8/24/99 | CDSR2 | 0% |
| 106 | Install addition Gigabit Ethernets (cabling from d0mino) | 1 day | Tue 8/24/99 | Tue 8/24/99 | SGI | 0% |
| 107 | Test filesystems | 1 day | Wed 8/25/99 | Wed 8/25/99 | 0% | |
| 108 | On D02ka | 1 day | Wed 8/25/99 | Wed 8/25/99 | CDSR2 | 0% |
| 109 | On D0test | 1 day | Wed 8/25/99 | Wed 8/25/99 | CDSR2 | 0% |
| 110 | Test Gigabit Ethernet | 1 day | Fri 10/8/99 | Mon 10/11/99 | CDSR2 | 0% |
| 111 | Fast Ethernet | 1 day | Mon 10/11/99 | Tue 10/12/99 | 0% | |
| 112 | Install Quad Ethernet board | 1 day | Mon 10/11/99 | Tue 10/12/99 | CDSR2 | 0% |
| 113 | Request/Move connections | 1 day | Mon 10/11/99 | Tue 10/12/99 | CDSR2 | 0% |
| 114 | NLBS testing | 1 day | Mon 10/11/99 | Tue 10/12/99 | CDSR2 | 0% |
| 115 | ||||||
| 116 | Backups | 68 days | Mon 8/2/99 | Wed 11/3/99 | 6% | |
| 117 | Backup plan | 3 days | Mon 8/2/99 | Wed 8/4/99 | CDS-D0 | 100% |
| 118 | Purchase Hardware/Media | 1 day | Thu 8/5/99 | Thu 8/5/99 | CDS-D0 | 100% |
| 119 | Wait for equipment | 60 days | Fri 8/6/99 | Thu 10/28/99 | 0% | |
| 120 | Install/test/Configure FMB/Juke | 3 days | Fri 10/29/99 | Tue 11/2/99 | CDSR2 | 0% |
| 121 | Configure for backup | 1 day | Wed 11/3/99 | Wed 11/3/99 | CDSR2 | 0% |
| 122 | ||||||
| 123 | NIS | 72 days | Thu 7/29/99 | Fri 11/5/99 | 7% | |
| 124 | Configuration problems (NLBS) | 12 days | Thu 7/29/99 | Fri 8/13/99 | 0% | |
| 125 | D0mino NIS Slave (?) / Configure NIS | 1 day | Mon 8/16/99 | Mon 8/16/99 | CDSR2[20%] | 100% |
| 126 | D0mino Master | 1 day | Fri 11/5/99 | Fri 11/5/99 | CDSR2 | 0% |
| 127 | ||||||
| 128 | SAM | 43.7 days | Fri 10/1/99 | Wed 12/1/99 | 0% | |
| 129 | Initial Testing | 1 day | Fri 10/1/99 | Mon 10/4/99 | 0% | |
| 130 | Testing w/ LSF | 1 day | Tue 10/12/99 | Wed 10/13/99 | 0% | |
| 131 | Testing w/Enstore | 1 day | Wed 12/1/99 | Wed 12/1/99 | 0% | |
| 132 | ||||||
| 133 | ENSTORE | 57 days | Mon 9/13/99 | Tue 11/30/99 | 0% | |
| 134 | Network (Gigabit Ethernet) Installation | 1 day | Mon 9/13/99 | Mon 9/13/99 | NET | 0% |
| 135 | Network Configuration | 1 day | Tue 10/5/99 | Wed 10/6/99 | CDSR2 | 0% |
| 136 | Testing | 1 day | Tue 11/23/99 | Tue 11/23/99 | ISD | 0% |
| 137 | MPADMIN/SYSMP | 5 days | Wed 11/24/99 | Tue 11/30/99 | ISD | 0% |
| 138 | ||||||
| 139 | D0MINO Early Bird | 5 days | Mon 9/13/99 | Fri 9/17/99 | 0% | |
| 140 | D0MINO General Availability | 1 day | Thu 11/4/99 | Thu 11/4/99 | 0% | |
| 141 | D0MINO Fully Functionable | 1 day | Wed 12/1/99 | Wed 12/1/99 | 0% |
| ID | Name | Group | Max Units | Peak Units |
|---|---|---|---|---|
| 1 | CDSR2 | 100% | 450% | |
| 2 | CDSR2-2 | 100% | 200% | |
| 3 | ISD | 100% | 100% | |
| 4 | D0 | 100% | 100% | |
| 5 | ? | 100% | 100% | |
| 6 | NET | 100% | 100% | |
| 7 | CDS-D0 | 100% | 100% | |
| 8 | SGI | 1,000% | 100% |
| Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
|---|---|---|---|---|---|---|
| 4 | Fibre-Channel Cards | CDSR2 | 2 hrs | Thu 7/15/99 | Thu 7/15/99 | 100% |
| 5 | Gigabit Ethernet | CDSR2 | 2 hrs | Thu 7/15/99 | Thu 7/15/99 | 100% |
| 6 | Downtime problems - Disk failures/Chassis | CDSR2 | 4 hrs | Fri 7/16/99 | Fri 7/16/99 | 100% |
| 7 | Raid disks | CDSR2 | 2 hrs | Mon 7/19/99 | Mon 7/19/99 | 100% |
| 8 | Fibre Disk Rack | CDSR2 | 2 hrs | Mon 7/19/99 | Mon 7/19/99 | 100% |
| 9 | Understanding Fibre-Channel Disk Technology | CDSR2 | 12 hrs | Wed 7/28/99 | Tue 9/28/99 | 100% |
| 10 | Raid configuration/partitioning | CDSR2 | 8 hrs | Wed 8/25/99 | Thu 8/26/99 | 100% |
| 14 | Export current homes | CDSR2 | 0.8 hrs | Tue 7/20/99 | Tue 7/20/99 | 100% |
| 15 | Identify RunII areas to export | D0 | 32 hrs | Mon 7/26/99 | Thu 7/29/99 | 100% |
| 16 | Export Current projects/tmps (RunII) | CDSR2 | 0.8 hrs | Fri 7/30/99 | Fri 7/30/99 | 100% |
| 18 | Move Homes Expansion consistent with backup | CDSR2 | 80 hrs | Mon 8/30/99 | Fri 9/10/99 | 100% |
| 20 | Balance of home made available | CDSR2 | 8 hrs | Thu 11/4/99 | Thu 11/4/99 | 0% |
| 21 | Add link to local | CDSR2 | 8 hrs | Tue 9/14/99 | Tue 9/14/99 | 0% |
| 23 | Allocate Hardware | D0 | 0 hrs | Thu 7/29/99 | Thu 7/29/99 | 100% |
| 25 | File System Plan/Identify RunII Data | D0 | 8 hrs | Wed 8/4/99 | Wed 8/4/99 | 100% |
| 26 | Implement Plan | CDSR2 | 8 hrs | Thu 8/19/99 | Thu 8/19/99 | 100% |
| 28 | Copy to new disks | CDSR2-2 | 120 hrs | Tue 8/24/99 | Tue 9/14/99 | 100% |
| 29 | Old Disk unavaialble | CDSR2 | 0 hrs | Tue 9/14/99 | Tue 9/14/99 | 100% |
| 30 | Move disks(cable) D0MINO | CDSR2 | 16 hrs | Tue 10/12/99 | Thu 10/14/99 | 0% |
| 34 | SGI Hardware Tests | SGI | 24 hrs | Tue 7/6/99 | Thu 7/8/99 | 100% |
| 35 | Hardware Configuration Plan | CDS-D0 | 8 hrs | Fri 7/9/99 | Fri 7/9/99 | 100% |
| 36 | Optional Hardware Configuration | CDS-D0 | 8 hrs | Mon 7/12/99 | Mon 7/12/99 | 100% |
| 37 | Disk Installation/Testing | CDSR2 | 16 hrs | Tue 7/13/99 | Wed 7/14/99 | 100% |
| 38 | Network Installation | NET | 24 hrs | Thu 7/15/99 | Mon 7/19/99 | 100% |
| 39 | System disk set (Plexing) | CDSR2 | 8 hrs | Mon 7/26/99 | Tue 7/27/99 | 100% |
| 40 | Install ssh/tcpwrappers | CDSR2 | 0.8 hrs | Wed 7/28/99 | Wed 7/28/99 | 100% |
| 42 | Mount User homes | CDSR2 | 0.8 hrs | Mon 8/2/99 | Mon 8/2/99 | 100% |
| 43 | Mount RunII Areas | CDSR2 | 0.8 hrs | Tue 8/3/99 | Tue 8/3/99 | 100% |
| 45 | SHARE | CDSR2 | 240 hrs | Tue 8/17/99 | Mon 9/27/99 | 0% |
| 47 | Patrol | CDSR2-2 | 24 hrs | Wed 8/25/99 | Fri 8/27/99 | 0% |
| 49 | Configuration Plan | CDS-D0 | 8 hrs | Thu 7/15/99 | Thu 7/15/99 | 100% |
| 50 | Installation | CDSR2 | 4 hrs | Mon 7/19/99 | Mon 7/19/99 | 100% |
| 51 | Investigation/Implementation | CDSR2 | 12 hrs | Tue 7/20/99 | Thu 7/22/99 | 100% |
| 52 | Testing | CDSR2 | 8 hrs | Fri 7/23/99 | Fri 7/23/99 | 100% |
| 53 | Co-Pilot | CDSR2 | 296 hrs | Mon 7/26/99 | Tue 9/14/99 | 95% |
| 58 | License | ISD | 24 hrs | Wed 8/4/99 | Fri 8/6/99 | 100% |
| 59 | LSF General Configuration Specs | CDS-D0 | 8 hrs | Mon 8/23/99 | Mon 8/23/99 | 100% |
| 60 | LSF Configuration | CDSR2-2 | 8 hrs | Mon 8/30/99 | Mon 8/30/99 | 0% |
| 61 | LSF SAM/ENSTORE Configuration | CDS-D0 | 8 hrs | Fri 8/13/99 | Fri 8/13/99 | 0% |
| 62 | LSF Configuration | CDSR2 | 8 hrs | Mon 10/11/99 | Tue 10/12/99 | 0% |
| 64 | Licenses | SGI | 8 hrs | Thu 7/22/99 | Thu 7/22/99 | 100% |
| 66 | Initial mount from d02ka | CDSR2 | 0.8 hrs | Tue 7/27/99 | Tue 7/27/99 | 100% |
| 69 | Installation | CDSR2 | 4 hrs | Thu 10/14/99 | Fri 10/15/99 | 0% |
| 70 | Configure System Backup | CDSR2 | 4 hrs | Thu 10/14/99 | Fri 10/15/99 | 0% |
| 72 | Installation | CDSR2 | 4 hrs | Mon 9/6/99 | Mon 9/6/99 | 100% |
| 73 | Lincense | ? | 8 hrs | Fri 9/10/99 | Fri 9/10/99 | 100% |
| 75 | Initial mount from d02ka | CDSR2 | 4 hrs | Fri 10/15/99 | Mon 10/18/99 | 100% |
| 79 | Allocate Hardware | D0 | 8 hrs | Tue 8/3/99 | Tue 8/3/99 | 100% |
| 81 | File System Plan | CDS-D0 | 8 hrs | Fri 8/6/99 | Fri 8/6/99 | 0% |
| 82 | Implement Plan | CDSR2 | 24 hrs | Tue 9/28/99 | Fri 10/1/99 | 0% |
| 84 | File System Plan | CDS-D0 | 8 hrs | Mon 9/13/99 | Mon 9/13/99 | 0% |
| 85 | Implement Plan | CDSR2 | 8 hrs | Mon 11/22/99 | Mon 11/22/99 | 0% |
| 87 | File System Plan | CDS-D0 | 8 hrs | Mon 8/30/99 | Mon 8/30/99 | 100% |
| 88 | Implement Plan | CDSR2 | 24 hrs | Thu 9/9/99 | Mon 9/13/99 | 100% |
| 90 | File System Plan | CDS-D0 | 8 hrs | Mon 8/9/99 | Mon 8/9/99 | 100% |
| 91 | Implement Plan | CDSR2 | 80 hrs | Tue 9/14/99 | Tue 9/28/99 | 100% |
| 93 | File System Plan | CDS-D0 | 8 hrs | Fri 9/10/99 | Fri 9/10/99 | 100% |
| 94 | Implement Plan | CDSR2 | 8 hrs | Mon 9/13/99 | Mon 9/13/99 | 100% |
| 95 | Copy D0DIST from D02KA | D0 | 8 hrs | Mon 10/4/99 | Mon 10/4/99 | 0% |
| 98 | UPS Products | CDSR2 | 8 hrs | Wed 10/13/99 | Thu 10/14/99 | 0% |
| 99 | D0 UPS Products | CDSR2 | 8 hrs | Thu 10/14/99 | Fri 10/15/99 | 0% |
| 102 | Split Rack From Domino | CDSR2 | 8 hrs | Fri 8/20/99 | Fri 8/20/99 | 100% |
| 103 | Understanding Multi interface problem | CDSR2 | 8 hrs | Mon 8/23/99 | Mon 8/23/99 | 0% |
| 105 | Request installation | CDSR2 | 8 hrs | Tue 8/24/99 | Tue 8/24/99 | 0% |
| 106 | Install addition Gigabit Ethernets (cabling from d0mino) | SGI | 8 hrs | Tue 8/24/99 | Tue 8/24/99 | 0% |
| 108 | On D02ka | CDSR2 | 8 hrs | Wed 8/25/99 | Wed 8/25/99 | 0% |
| 109 | On D0test | CDSR2 | 8 hrs | Wed 8/25/99 | Wed 8/25/99 | 0% |
| 110 | Test Gigabit Ethernet | CDSR2 | 8 hrs | Fri 10/8/99 | Mon 10/11/99 | 0% |
| 112 | Install Quad Ethernet board | CDSR2 | 8 hrs | Mon 10/11/99 | Tue 10/12/99 | 0% |
| 113 | Request/Move connections | CDSR2 | 8 hrs | Mon 10/11/99 | Tue 10/12/99 | 0% |
| 114 | NLBS testing | CDSR2 | 8 hrs | Mon 10/11/99 | Tue 10/12/99 | 0% |
| 117 | Backup plan | CDS-D0 | 24 hrs | Mon 8/2/99 | Wed 8/4/99 | 100% |
| 118 | Purchase Hardware/Media | CDS-D0 | 8 hrs | Thu 8/5/99 | Thu 8/5/99 | 100% |
| 120 | Install/test/Configure FMB/Juke | CDSR2 | 24 hrs | Fri 10/29/99 | Tue 11/2/99 | 0% |
| 121 | Configure for backup | CDSR2 | 8 hrs | Wed 11/3/99 | Wed 11/3/99 | 0% |
| 125 | D0mino NIS Slave (?) / Configure NIS | CDSR2 | 1.6 hrs | Mon 8/16/99 | Mon 8/16/99 | 100% |
| 126 | D0mino Master | CDSR2 | 8 hrs | Fri 11/5/99 | Fri 11/5/99 | 0% |
| 134 | Network (Gigabit Ethernet) Installation | NET | 8 hrs | Mon 9/13/99 | Mon 9/13/99 | 0% |
| 135 | Network Configuration | CDSR2 | 8 hrs | Tue 10/5/99 | Wed 10/6/99 | 0% |
| 136 | Testing | ISD | 8 hrs | Tue 11/23/99 | Tue 11/23/99 | 0% |
| 137 | MPADMIN/SYSMP | ISD | 40 hrs | Wed 11/24/99 | Tue 11/30/99 | 0% |