Joint CDF/D0/CD Run II Computing Project

cdf logo d0 logo cd logo


The Run II Joint Project has transitioned to the commissioning and operations phase. Operations MOUs between the Collaborations and the Computing Division are being developed.

An Operations Needs Assessment is being developed. The Joint Project is working on  integration issues for  CDF and D0 . The Fermilab long range schedule defines when beam is expected. Mock Data Challenge and Data Handling (DAQ through analysis) milestones need to be met on the way.


Infrastructure Data Storage  Data Access Production and Analysis
Zoom - C++ utility library (maillist) Robotic Hardware CDF Data Handling Production Hardware (maillist)
Databases Support (maillist) 12/12/99: 7/25/00 Enstore Data Storage System (maillist) D0 Data Access - SAM 8/21/00, (maillist) Production Management (maillist)
Simulation and Generators Serial Media
Final Report , (maillist)
Networking Hardware Physics Analysis Software
1999
Configuration Management (maillist) Reconstruction Input Pipeline Physics Analysis Hardware Visualization (maillist) check1.gif (1015 bytes)
Project Documents             check1.gif (1015 bytes) = Status Reports available

Background:

The Joint CDF/D0/CD Run II Computing Project consists of a number of common projects and associated working groups to address the offline computing needs of D0 and CDF for Run II. The needs are defined through the two reports of the Needs Assessment Group (NAG)< as a result of its charge. The group had the following members.

The project is described by the Project Management Plan, found here, and its Work Breakdown Structure. It has the following organization under the umbrella of the Steering Committee. Run II Joint Offline Committee meetings have Minutes. (1998 and 1997 and 1996). Project Status reports are available for Mar '99, Jan '99 and Nov '98. To register a document use the following form. The contents of the RunIIComputing mail list is available and you can request to be added to it. Apply here if you want to video conference to the meetings. Mail all comments on these web pages to the RunIISteering mail list.

A Review Committee with the following charge was appointed for the Joint Computing Project with the following meetings: June 1997: Agenda & Report html, ps.  October 1997: Agenda  & Report html, ps. June 1998: Agenda & Report html, ps. Jan 1999: Agenda & Report html  ps.  June 1999: Agenda